Word package number WP12
Type of activity Other specific activities
Wordk Package title Dissemination Activities
Start month 1
End month 30
Lead beneficiary CIMA Research Foundation

 

Objectives

This work package focuses on disseminating and outreaching the project objectives and results by demonstrating the accessibility and benefits of RASOR tools in Disaster Risk Management at global and European level.
Consequently, the main objectives are:

  • to demonstrate the project solutions to stakeholders/End Users (MIC, EEAS, COPERNICUS/GMES related
    project and GIO service providers, International Organisations involved in disaster Prevention, response and reconstruction, Disaster Managers mainly at Country level);
  • to raise the project awareness at the European and global level in:

    • DRR user communities;
    • Earth Observation communities;
    • Related projects;
  • to promote capacity building to the End Users that expressed their support to the project, favoring the uptake of RASOR tools in their prevention and reconstruction policies.

The specific means to achieve these objectives are:

  1. preparation and distribution of adequate information material including a periodic RASOR e-Newsletter;
  2. active participation in conferences and workshops involving the target communities identified above;
  3. media and press releases;
  4. organisation of a RASOR User Forum. A web 2.0-style platform will be set up for the RASOR User Forum that will facilitate the contacts with the End Users supporting the project and attract other potential Users, gathering continuous feedbacks during the project duration.

 

List of Tasks

T12.1 – Dissemination Action Plan [Months: 1-28]
T12.2 – RASOR web site set-up and management [Months: 3-30]
T12.3 – RASOR e-Newsletter [Months: 3-30]
T12.4 – Production and dissemination of promotional and training material [Months: 1-23]
T12.5 – RASOR User Forum [Months: 1-17]
T12.6 – Organisation and assessment of capacity building workshops [Months: 12-15]
 
 

List of deliverables

Deliverable
Number
Deliverable Title Lead beneficiary Nature Dissemination
level (*)
Delivery
date
D12.1 RASOR DAP (1st Release) CIMA Research Foundation Report PP 6
D12.2 RASOR DAP (2nd Release) CIMA Research Foundation Report PP 28
D12.3 RASOR Web-Site CIMA Research Foundation Other PU 30
D12.4 RASOR 1st e-Newsletter CIMA Research Foundation Report PU 6
D12.5 RASOR 2nd e-Newsletter CIMA Research Foundation Report PU 12
D12.6 RASOR 3rd e-Newsletter CIMA Research Foundation Report PU 18
D12.7 RASOR 4th e-Newsletter CIMA Research Foundation Report PU 24
D12.8 RASOR 5th e-Newsletter CIMA Research Foundation Report PU 30
D12.9 First version of RPK CIMA Research Foundation Other PU 8
D12.10 First Revision of RPK CIMA Research Foundation Other PU 12
D12.11 Second Revision of RPK CIMA Research Foundation Other PU 18
D12.12 Third Revision of RPK CIMA Research Foundation Other PU 24
D12.13 Fourth Revision of RPK CIMA Research Foundation Other PU 30
D12.14 RASOR User Forum Platform ACROTEC SRL Prototype PU 1
D12.15 First Dissemination Report CIMA Research Foundation Report PU 12
D12.16 Second Dissemination Report CIMA Research Foundation Report PU 24
D12.17 Third Dissemination Report CIMA Research Foundation Report PU 30
D12.18 User Workshop CIMA Research Foundation Other PU 13
D12.19 RASOR Conference CIMA Research Foundation Other PU 25

 
(*)
PU -> Public
PP -> Restricted to other programme participants (including the Commission Services)

Related files
RASO 1st e-NewsLetter  Download
WP: WP12 - Task: T12.3 - Deliverable: D12.4 - Status: Complete - Commission: n.a. - by cima
2nd RASOR e-Newsletter  Download
WP: WP12 - Task: T12.3 - Deliverable: D12.5 - Status: Complete - Commission: n.a. - by cima
1st Version of RDTK  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.9 - Status: Complete - Commission: n.a. - by cima
Periodic Dissemination Report v2  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.15 - Status: Complete - Commission: n.a. - by cima
RASOR USER FORUM  Download
WP: WP12 - Task: T12.5 - Deliverable: D12.14 - Status: Complete - Commission: n.a. - by cima
First Revision of the RTDK v2  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.10 - Status: Complete - Commission: n.a. - by cima
3-rd RASOR e-Newsletter  Download
WP: WP12 - Task: T12.3 - Deliverable: D12.6 - Status: Complete - Commission: n.a. - by cima
2nd Revision of the RDTK  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.11 - Status: Complete - Commission: n.a. - by cima
User Workshop Report  Download
WP: WP12 - Task: T12.6 - Deliverable: D12.18 - Status: Complete - Commission: n.a. - by cima
Third Revision of the RTDK  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.12 - Status: Complete - Commission: n.a. - by cima
D12.19 Community of Practice Inaugural Meeting Report  Download
WP: WP12 - Task: T12.6 - Deliverable: D12.19 - Status: Complete - Commission: n.a. - by athena
RASOR Web-Site  Download
WP: WP12 - Task: T12.2 - Deliverable: D12.3 - Status: Complete - Commission: n.a. - by cima
RASOR 4th e.Newsletter  Download
WP: WP12 - Task: T12.3 - Deliverable: D12.7 - Status: Complete - Commission: n.a. - by cima
RASOR 5th e.Newsletter  Download
WP: WP12 - Task: T12.3 - Deliverable: D12.8 - Status: Complete - Commission: n.a. - by cima
Fourth Revision of the RTDK  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.13 - Status: Complete - Commission: n.a. - by cima
Second Dissemination report  Download
WP: WP12 - Task: T12.4 - Deliverable: D12.16 - Status: Complete - Commission: n.a. - by cima
Third Dissemination Report  Download
WP: WP12 - Task: T12.1 - Deliverable: D12.17 - Status: Complete - Commission: n.a. - by cima